Question: 1
Assessing the probability and consequences of identified risks to the project objectives, assigning a risk score to each risk, and creating a list of prioritized risks describes which of the following processes?
A. Identify Risks
B. Qualitative Risk Analysis
C. Quantitative Risk Analysis
D. Plan Risk Management
Answer: B
Question: 2
Which of the following characteristics of baseline represents specification that is used to identify approved requirements in baseline modeling?
A. Functional
B. Allocated
C. Product
D. Developmental
Answer: B
Question: 3
Which of the following variables are associated with quantitative assessment of risks? Each correct answer represents a complete solution. Choose three.
A. Impact
B. Probability
C. Cost
D. Frequency
Answer: D, B, A
Question: 4
Which of the following laws applies to organizations handling health care information?
A. SOX
B. GLBA
C. HIPAA
D. FISMA
Answer: C